CityGo Route Changes

OCCK Transportation is implementing an annual route change process. Every year, staff reviews routes, ridership data, and schedules, and proposes route changes to the bus riding public. To get robust feedback, in-person and virtual survey opportunities are provided. This page collects all the information you need to engage in this process.

Route changes for 2025 will go into effect on September 8, 2025: faster rides, stronger connections. August 4, 2025, will be the discontinuation of Blue Peak.

Links

Public Engagement

Downtown (7th & Walnut) 

  • 6/20: 11:00am-1:00pm

New Route Features

Changes:

2025 Time Tables:

Status + Timeline + Next Steps

Status:

  • Complete. Route changes for 2025 started September 8, 2025. August 4th was the discontinuation of Blue Peak.

Timeline:

  • Milestone 1: Public Outreach Period (April 2025) – Complete
  • Milestone 2: Survey data analysis (May 2025) – Complete
  • Milestone 3: Closing the Loop: Present final routes to the public (June/July 2025) – Complete
  • Milestone 4: Rider Guide Production (May 2025 – July 2025) – Complete
  • Milestone 5: New Routes go into effect (September 2025) – Complete

Next Steps:

  • New CityGo routes are running as of September 8, 2025.
  • Watch for new route guides and maps.